Spencerville Local School District

New Building Progress


See the Construction Progress - Click on the Links Below

05/20/05 Update        06/09/05 Update        06/20/05 Update

07/07/05 Update        07/28/05 Update        09/02/05 Update

09/12/05 Update (Aerial views)                 10/03/05 Update

10/18/05 Update        11/10/05 Update       12/14/05 Update 

01/12/06 Update        02/02/06 Update       03/07/06 Update

04/25/06 Update        05/17/06 Update        06/09/06 Update

08/11/06 Update       09/25/06 Update       10/20/06 Update

11/16/06 Update

                                                           

April 1, 2005 Groundbreaking Ceremony - Click to see Photos

Click below to see the site layout and some preliminary building views.

k12-site.jpg (325542 bytes)

k12-1.jpg (34032 bytes)     k12-2.jpg (42560 bytes)     k12-3.jpg (37911 bytes)     k12-5.jpg (42429 bytes)     k12-4.jpg (43693 bytes)     

 



 
 
Tentative Timeline
March 2004  - Board Approval Program of Requirements
October 2004 - Board Approval of Design Development
December 2004 - Board Approval of Construction Documents
January 2005 - Solicit Bids
February 2005 - Open Bids
March 2005 - Board Approval of Prime Contractors
April 2005-October 2006 - Building Construction
November 2006 - Final Inspection
December 2006 - District Move-In
Schedule prepared by Touchstone Bostleman, construction manager

 